International Technology Scanning Program Sponsored by: US Department of Transportation, Federal Highway Administration May 2009 NOTICE The Federal Highway Administration provides high-quality information to serve Government, industry, and the public in a manner that promotes public understanding. Standards and policies are used to ensure and maximize the quality, objectivity, utility, and integrity of its information. FHWA periodically reviews quality issues and adjusts its programs and processes to ensure continuous quality improvement. Acknowledgments The authors wish to express their gratitude toward the numerous individuals who helped contribute the information in this report. The following provided key source information about the German practice:
The following worked on the Missouri and Oklahoma demonstration projects and provided additional information:
Early in this project, an expert technical group was formed. In addition to many of the individuals previously mentioned, the following people also offered their time and assistance:
Finally, the following geotextile representatives assisted in the preparation of this report:
Executive SummaryPavement engineering is traditionally a conservative field, but successful pavement engineers will constantly seek out proven innovative concepts with potential to improve pavement performance while reducing costs. Many pavement structures in the United States consist of more than one cementitious layer that requires separation. This could be a new concrete pavement (jointed or continuously reinforced) atop a cementitious base or, becoming increasingly popular, an unbonded concrete overlay. In both cases, an interlayer is often required for separation. While hot-mix asphalt is commonly used for this purpose, associated constructability, cost, and performance issues need to be recognized. The German highway community has more than 25 years of experience using an alternative interlayer made of a nonwoven geotextile. With proper selection and placement, these interlayers have resulted in excellent performance in separating new concrete pavement layers from the cementitious bases commonplace on the German motorway system. While this application also exists in the United States, the possibility of using the nonwoven geotextile as a separation interlayer in an unbonded concrete overlay system has also generated significant interest because of the potential cost savings involved. This report documents the German experience and gleans better practices for using nonwoven geotextile interlayers between cementitious layers in the United States. The report covers field trials in Missouri and Oklahoma along with other information so that pavement engineers can make an informed decision on the viability of this innovative but proven alternative. BackgroundIn May 2006, a team of public and private sector representatives participated in a scanning study of long-life concrete pavements sponsored by the Federal Highway Administration (FHWA), the American Association of State Highway and Transportation Officials (AASHTO), and the National Cooperative Highway Research Program (NCHRP). During this scan, the team learned about the German use of nonwoven geotextile as an interlayer between lean concrete bases and concrete pavement surfaces.(1) As a result of the scan, the team concluded that nonwoven geotextile has potential benefit in U.S. practice as an interlayer between cementitious layers. It was decided that field trials should be undertaken with a geotextile interlayer-not just as the Germans had demonstrated it, but also to separate old concrete pavement from new concrete overlays. This report documents the state of the practice in Germany, along with the results of two field trials in the United States, including an unbonded concrete overlay project in Missouri and a project in Oklahoma that used the geotextile to separate a cement-treated base from a new concrete pavement. State of the Practice in GermanyCementitious bases are commonly used throughout Germany. For decades, they have served as part of the pavement structures for jointed concrete pavements. It was clearly demonstrated during the long-life concrete pavements scan that the German highways are of high quality and have sustained long lives under significant traffic.(1) Until about 20 years ago, no particular effort was made to encourage or break the bond that may have developed between the two cementitious layers. Reflection cracking that would otherwise occur in some instances was controlled by notching the surface of the cementitious base during its construction. These notches were matched with the saw cuts that defined the joints of the overlying concrete surface. Like nearly all highway systems, though, some areas on the German network experienced premature failures. On the German motorway A5 in 1981, during the course of a pavement repair contract, an idea was born.(2) Several slabs had experienced cracking failure because of what appeared to be a loss of support. Further investigation determined that the cementitious base had partially pulverized because of hydraulic pressures caused by infiltration and collection of water at the interface between the base and the surface. The pulverized fines pumped to the surface, which led to the loss of support. In turn, the void that had formed between the two cementitious layers caused the cracking. Recognizing that poor drainage contributed to this failure, the Germans decided to place a nonwoven geotextile atop the existing cementitious base before replacing the concrete slabs. The edges of the geotextile terminated on top of an existing longitudinal drainage system. After this test section had proven to be a success, additional trials of this technique were used in other locations throughout Germany, including application during new construction. Over time, the Germans found that the geotextile served as an ideal replacement for the practice of notching the cementitious base and made its use a standardized practice. Critical Material Properties of Geotextile InterlayersThe theory behind the use of nonwoven geotextile interlayers is based on three critical functions:(3)
Over the years, the Germans have learned what properties of the nonwoven geotextile material can improve one of these three functions. They have also learned the tradeoffs that sometimes exist when improvements made to one function compromise another. As a result, the evolution of German specifications reflects the optimization of the material. Specification and Design ProceduresUse of the geotextile interlayer was first standardized as a national practice in Germany in 2001 through the pavement catalog (Richtlinie für die Standardisierung des Oberbaues von Verkehrsflächen, RStO 01).(4,5) An excerpt of the RStO is illustrated in figure 1, which shows the use of the interlayer for all concrete pavement sections containing a cementitious base layer. The RStO does include options for asphalt treated and unbound aggregate bases, but the interlayer is not used in those instances. Figure 1. Highlighted excerpt of German pavement design catalog (RStO). Standard details and methods for the geotextile were published as part of the concrete pavement guide document, Zusätzliche Technische Vertragsbedingungen und Richtlinien für den Bau von Fahrbahndecken aus Beton (ZTV Beton-StB 01).(6) This has recently been revised as ZTV Beton-StB 07. Additional material properties for the interlayer are also published in the companion standard, Technische Lieferbedingungen für Baustoffe und Baustoffgemische für Tragschichten mit hydraulischen Bindemitteln und Fahrbahndecken aus Beton (TL Beton-StB 07).(7) Given the rapidly expanding knowledge base on the use of these interlayers, the Germans decided to develop a separate standard. A committee of practitioners in Germany is developing a draft of the standard, which is expected to be published in mid to late 2009. Table 1 includes a summary of materials specifications derived from the guidance in TL Beton-StB 07 and ZTV Beton-StB 07, along with the result of numerous discussions with German practitioners. This table should be considered a starting point for the specification of nonwoven geotextile interlayers in the United States. It should be stressed, however, that while preliminary attempts have been made to find test standards more commonly used in the United States (e.g., ASTM), the original (e.g., ISO, EN, DIN) tests should be considered the standard until full equivalency can be verified. In the interim, a list of accredited laboratory facilities capable of conducting these tests is on the Geosynthetic Institute Web site (www.geosynthetic-institute.org).
Available ProductsThe critical properties of separation, drainage, and bedding require that the geotextile material possess a number of critical material properties. While nonwoven geotextile materials are commonly used in the United States for a multitude of applications, there is no known demand for materials used in the same manner as the German interlayer. As a result, nonwoven geotextiles are not yet marketed domestically for this purpose, so they do not necessarily meet all of the recommended interim specifications. Based on a series of Internet searches and discussions with industry representatives in the United States and Germany, table 2 includes a list of products that have been used or have potential for use for interlayer application in a manner similar to what is specified in Germany. In addition to materials manufactured in the United States, materials can be imported from Germany. This option reportedly was exercised on the Oklahoma field trial described in this report. In the end, market forces will drive the availability and cost of fully compliant materials. Meanwhile, both domestic and imported sources appear to be viable options. Worth noting is that importation of the geotextile can increase lead time, reportedly by 6 to 8 weeks.
Construction Installation PracticesPavement construction using the nonwoven geotextile interlayer has been a reported a success in U.S. field trials so far. In addition, the Germans report ease in construction. The following is a summary of better construction practices reported in various German guidelines and related publications:
CostThe installed cost of a nonwoven geotextile interlayer appears to range from $1.50 to $2.50 per square yard (yd2). The in-place cost in Germany has been reported to be as little as $1.10 per yd2. In 2006, it was reported that the material cost in Germany was about $1.00 per yd2. Recent discussions (in 2009) with German vendors verified a material price of about $0.90 to $1.00 per yd2 FOB source/origin. If material is ordered from Europe, sea freight costs of $0.05 to $0.10 per yd2 can be expected. Additional costs will apply for taxes or tariffs (possibly 10 to 15 percent) and for transport between the port terminal and the project site. Installation costs can vary, but costs of $0.10 to $0.50 per yd2 are believed reasonable based on information reported from German practitioners and from the field trials to date in the United States. Quality Assurance ConceptsQuality assurance of the nonwoven geotextile should be achieved through periodic sampling and testing. As a starting point for a proposed sampling plan, the first samples should be collected after placement of about 1,000 m2 (1,200 yd2), a second sample after 10,000 m2 (12,000 yd2), and additional samples collected every 10,000 m2 (12,000 yd2) thereafter. Each sample is typically 1 m2 (1.2 yd2) in size and should not be taken from the first or last two "windings" on the roll. A specific testing schedule for the various items reported in table 1 will require further investigation. This should include additional consultation with the Germans, who continue to formalize this in their standard practices. Worth noting is footnote 1 in table 1, which states that the material in Germany is required to comply with the specifications for 95 percent of the samples tested. This requirement contrasts with minimum average roll value (MARV) requirements commonly specified for geotextiles in the United States, which require a 97.7 percent degree of confidence (see AASHTO M 288). Preliminary Field Trials in the United StatesAs part of this project, the project team evaluated two projects-one in Missouri and one in Oklahoma-that used a nonwoven geotextile interlayer. This section summarizes the trials. Missouri, Route D, Cass and Jackson CountiesDuring summer 2008, an unbonded concrete overlay project was constructed on Route D (Holmes Road) spanning the border of Cass and Jackson Counties south of Kansas City, MO (see figure 2). On this project, nonwoven geotextile interlayer was specified as an alternative to the conventional 1-in (25.4-mm) hot-mix asphalt (HMA) interlayer. The intent was to separate the 22-year-old, 8-in (203-mm) existing concrete pavement surface from the proposed 5-in (127-mm) unbonded concrete overlay. While the interlayer does separate two cementitious-bound layers, this application differs from the typical German practice of separating a cementitious base from a new concrete pavement. In the few instances in Germany in which a nonwoven geotextile was used to separate two concrete layers, the existing concrete pavement was rubblized first. Figure 2. Map of Missouri Route D project. Construction of the project was highlighted at an open house sponsored by the Missouri-Kansas Chapter of the American Concrete Pavement Association (ACPA), Missouri and Kansas Departments of Transportation (DOTs), FHWA, and National Concrete Pavement Technology Center. The August 13, 2008, event and included a half-day of presentations followed by an onsite field review of the project, which was about half paved. During the open house, those attending were introduced to the German practice, along with the specific design and construction elements of the Route D project. In theory, as an overlay interlayer, the nonwoven geotextile must prevent reflection of the distress of the existing concrete pavement while providing a stable and drainable platform for the overlay. Following these principles, two nonwoven geotextiles were used for various parts of the project, including Geotex 1201 and Geotex 1601, manufactured by Propex. It was recognized that these geotextiles did not fully comply with the German specifications, but because they were immediately available and complied with some of the more critical aspects of the German specification, they were considered viable for use on this project. Some concern was raised initially with the lighter geotextile (Geotex 1201) about what appeared to be areas of the geotextile that were thinner than the German specification. As shown in figure 3, the material not only appeared thin, but also had areas that appeared to be partially melted. Further investigation confirmed that the Geotex geotextile is normally exposed to heat (calendared or infrared (IR)) to partially fuse one side of the material. What was observed was likely material from the end of a production run, where excess heat was inadvertently applied. Figure 3. Undesirable thinness and partial melting of isolated areas of the Geotex 1201 compared to a thicker geotextile known to fully comply with German specifications. Subsequent discussions of this phenomenon with experts in Germany did not yield significant concern, but did underscore the German practice of discouraging the use of geotextiles with thermal treatment. While firsthand observations were not made of the subsequent use of the Geotex 1601 material, it is believed that the denser material would be more likely to partially mitigate potential drawbacks of the thermal treatment. Furthermore, subsequent testing of the 1601 material has confirmed compliance with all but the thermal treatment requirements in the proposed interim specifications. The Route D overlay project is believed to be typical of upcoming projects in Missouri. As illustrated in figure 4, the existing concrete pavement is experiencing severe durability cracking (D-cracking), defined by the significant deterioration of the concrete near the pavement joints. Investigation of the structural capacity of the pavement, however, led to the possibility of an unbonded concrete overlay as a viable rehabilitation. As part of the project, the Missouri DOT offered an option to use a nonwoven geotextile interlayer in lieu of a 1-in (25.4-mm) Figure 4. Typical existing pavement condition along Route D before overlay. Before placement of the overlay, patching and repair of the damaged concrete near the joints was undertaken unless an existing patch appeared intact and flush with the existing pavement surface. Where applied, the repair technique used on this project included removal of all existing patch and loose material from these areas. This was followed by placement of a flowable (cementitious-based) fill. The completed repairs are shown in figure 5. Figure 5. Repair and replacement of damaged concrete with flowable fill. The geotextile material was delivered to the project on 300-ft (91-m) rolls, 15 ft (4.5 m) wide. As illustrated in figure 6, a telescopic forklift was used to transport the rolls from the yard to the roadway and to assist with application. Figure 6. Transport and application of geotextile from rolls along Route D project. On the Route D project, a Hilti gas-powered system was used to drive the fasteners (collated pins) into 2.25-in (57 mm) metal discs, through the geotextile, and into the underlying concrete pavement. This is illustrated in figure 7. A string of pins and underside of the disc are shown in figure 8. Figure 7. Fastening geotextile to existing concrete pavement along Route D project. Figure 8. Hilti X-GN/X-GHP fasteners (collated pins) and discs used for Route D project. As part of the installation process, two rolls of geotextile were used to span the width of the pavement. As a result, both longitudinal and transverse lapping of the geotextile were necessary, as illustrated in figure 9. Figure 9. Overlap of geotextile on Route D project. Immediately before construction, the geotextile material was wetted using a tanker truck, shown in figure 10. The surface was reportedly saturated, and it was later concluded that less water would ensure more ideal moisture content. Figure 10. Prewetting of geotextile before paving Route D project. Construction of the overlay is illustrated in figure 11. No problems were reported with the geotextile during the paving process. In general, the project proceeded as it would have using a conventional interlayer. Figure 11. Overlay placement along Route D project. After construction, cores were extracted from the pavement structure. As shown in figure 12, the geotextile was found to have bonded to the fresh concrete. Bonding did not occur between the geotextile and the underlying concrete pavement, which is ideal considering the necessity for separation from this layer. Figure 12. Core of Route D project showing overlay bonded to geotextile interlayer (underlying pavement not bonded, so core cannot be extracted). Overall, the Route D project appears to be a success. It has been reported that the long-term performance of this section will be monitored. Oklahoma, Westbound I-40, WarnerIn fall 2008, a new concrete paving project along westbound Interstate 40 in Oklahoma provided a second opportunity to evaluate the German interlayer. In this case, the project was similar to the typical German application with the interlayer used to separate a new cement-treated base (CTB) from a new concrete pavement. A map of the project, constructed by Duit Construction, Inc., is shown in figure 13. Figure 13. Map of Oklahoma I-40 project. On this project, the geotextile selected was imported from Germany. The product, HaTe nonwoven B 500, is manufactured and distributed by the U.S. subsidiary of Huesker Synthetic GmbH. Figure 14 shows the rolls of geotextile delivered directly to the project and placed atop the new CTB. Immediately before the paving, a modified backhoe loader was used to lift the rolls and assist in the installation. A crew of three to five people installed the geotextile, as shown in figure 14 and figure 15. The wrinkles observed to the right of figure 15 should be minimized to the greatest extent practical. Figure 14. Delivery and installation of geotextile rolls on I-40 project. Figure 15. Geotextile installation on I-40 project. The geotextile was fastened to the underlying CTB using a Hilti powder-actuated system with X-DNI fasteners (consisting of integrated pins and washers), as shown in figure 16 and figure 17. The washers used on this project are smaller than those recommended in German practice. Additional care may be necessary to ensure that the geotextile does not tear free of these fasteners during subsequent concrete placement. Figure 16. Fastening geotextile to CTB on I-40 project. Figure 17. Hilti X-DNI fasteners used on I-40 project. The 5-m-wide (5.4-yd-wide) geotextile rolls were placed two across, resulting in a need for both longitudinal and transverse laps as shown in figure 18. Figure 18. Lapping seams of geotextile on I-40 project. The majority of the geotextile appeared to be in good to excellent condition. Two haul roads flanked the project, limiting the need for vehicle maneuvering atop the installed geotextile. As figure 19 shows, however, an isolated instance of shoving was observed, likely because of a short-radius turning maneuver. The severity of the shoving does not appear to be significant enough to warrant replacing the geotextile, but it underscores the need to avoid the potential for its occurrence. Figure 19. Localized shoving of geotextile due to short-radius truck turning maneuver. Paving on the geotextile appeared to proceed with no variance from normal construction procedures. As shown in figure 20, haul trucks traveled on the geotextile, backed up to the paver, and deposited the fresh concrete onto the geotextile in advance of the spreader. As illustrated in figure 21, the edge of the geotextile was not damaged by the paver and appeared behind the paving train intact. Figure 20. Paving new concrete pavement on geotextile on I-40 project. Figure 21. Geotextile terminating under shoulder on I-40 project. Figure 22 shows a core sample removed from the I-40 project. It shows the separation of the two cementitious layers, along with a slight bonding of the geotextile to the new concrete pavement. Figure 22. Core of I-40 project showing new concrete bonded to geotextile interlayer (underlying CTB not bonded). The project in Oklahoma appeared to be a success. The contractor believed it saved money and time without compromising performance. Conclusions and Recommendations for Further EvaluationIt appears from both the literature and firsthand field observations that the use of a nonwoven geotextile interlayer between cementitious layers is not only viable, but also potentially a superior alternative to more conventional interlayer materials. Benefits of the nonwoven geotextile interlayer include the following:
While nonwoven geotextiles are used routinely as an interlayer between concrete pavements and cementitious bases, more performance data are needed to demonstrate their use in unbonded concrete overlay applications. Experience to date in Germany for the latter has included rubblization or crack-and-seat of the existing concrete pavement before placement of the geotextile and overlay. The fundamental properties of the nonwoven geotextile make it a likely candidate as a viable alternative to a hot-mix asphalt interlayer, however. This is particularly true if measures are taken to minimize the potential for mechanical "keying" of the two concrete layers. In Missouri, for example, distressed concrete at the joints was removed and replaced with a flowable fill. Theoretically, this measure should help reduce the potential for reflective distress. Monitoring of this and other unbonded concrete overlays is warranted, especially because of the significant potential benefits the nonwoven geotextile interlayer offers for this type of application. Another question raised is on the process of eventual removal of concrete pavement placed atop the geotextile. The Kansas DOT reported one experience with this on a short section of concrete placed on a thin nonwoven geotextile interlayer employed as a "bond breaker." Years later, the pavement had experienced high-severity D-cracking, and during panel replacement the concrete, which had bonded securely to the geotextile, was difficult to remove. As shown in figure 23, full-depth segmenting of the panels was necessary to remove the concrete with conventional heavy equipment. Figure 23. Removal of concrete pavement from a thin nonwoven geotextile in Kansas. It should be stressed, however, that the material used in Kansas was reported to be significantly thinner than the material recommended for use. As a result, it is likely that the material was more completely saturated with the mortar, thus leading to increased bonding. German practice and the projects documented in this report do not show this propensity for bonding when the thicker nonwoven geotextile is used. The Germans continue to seek more effective methods to separate the geotextile from concrete pavements since it is German practice to crush and reuse the concrete layer as recycled concrete aggregate. One last item identified during this effort was the idea of using an adhesive in lieu of mechanical fasteners to secure the geotextile to the underlying cementitious layer. German practice does specify the use of an approved adhesive when the geotextile is placed atop a waterproofed bridge deck (presumably since the fasteners would compromise the waterproofing layer). The approval process appears to be based on the experience of the project engineer, so additional information needs to be collected about specific materials and practices that could be used for this purpose. Endnotes(1) Hall, K., et. al., Long-Life Concrete Pavements in Europe and Canada, FHWA-PL-07-027, Federal Highway Administration, Washington, DC, August 2007. (2) Sulten, P., and W. Wilmers, "Use of Geotextiles in Concrete Pavement Construction," Proceedings of the Second European Geosynthetics Conference, Bologna, Italy, 2000, pp. 437-442. (3) Wilmers, W., "Geosynthetics in Road Construction-German Regulations," Proceedings of the Seventh International Conference on Geosynthetics, Nice, France, 2002. (4) Forschungsgesellschaft für Straßen- und Verkehrswesen Arbeitsgruppe Betonstaßen, Richtlinie für die Standardisierung des Oberbaues von Verkehrsflächen (RStO), 2001. (5) Leykauf, G., and D. Birmann, "Concrete Pavements with Geotextile Interlayer in Germany-Measurements and Long-Term Behaviour," Proceedings of the Tenth International Symposium on Concrete Roads, Brussels, Belgium, Sept. 8-22, 2006. (6) Forschungsgesellschaft für Straßen- und Verkehrswesen Arbeitsgruppe Betonstaßen, Zusätzliche Technische Vertragsbedingungen und Richtlinien für den Bau von Fahrbahndecken aus Beton (ZTV Beton-StB), 2001 (updated 2007). (7) Forschungsgesellschaft für Straßen- und Verkehrswesen Arbeitsgruppe Betonstaßen, Technische Lieferbedingungen für Baustoffe und Baustoffgemische für Tragschichten mit hydraulischen Bindemitteln und Fahrbahndecken aus Beton (TL Beton-StB), 2007. (8) Harrington, et. al., Guide to Concrete Overlays-Sustainable Solutions for Resurfacing and Rehabilitating Existing Office of International Programs PDF files can be viewed with the Acrobat® Reader®
|
More InformationContactHana Maier |
|||||||||||||||||||||||||||||||||||||||||||||||||||